How Long Does It Take to Build a Swimming Pool?
If you’re dreaming of a new pool in Shepparton, Echuca, Bendigo, or Wangaratta, one of the first questions is: “How long will it take?” The answer depends on a few key factors.
Factors That Affect Pool Build Time
- Pool Type
- Concrete pools in Shepparton: Highly customizable but can take 8–12 weeks to complete.
- Fibreglass pools in shepparton: Pre-moulded and faster – typically 2–4 weeks once the site is ready.
- Permits and Approvals
- Council approvals, fencing requirements, and safety inspections can affect timelines. Plan for 4–8 weeks depending on your local council.
Typical Timeline Overview
| Stage | Approx. Time |
|---|---|
| Design & planning | 1–2 weeks |
| Excavation & groundwork | 1–2 weeks |
| Shell construction | 2–6 weeks |
| Plumbing & electrical | 1–2 weeks |
| Finishing (tiles, coping, landscaping) | 1–3 weeks |
| Water fill & commissioning | 1 week |
The Bottom Line
On average, building a pool takes 6–12 weeks, but it can be shorter or longer depending on your pool type, site conditions, and approvals. With good planning, you’ll be diving into your dream pool before you know it.